top of page
The+Jackson_2nd+floor+kitchen+living+room.jpg

Group 12 Jackson

Project Progress

Jackson

May 2024

The units have all been framed, sheetrock has been commenced.


All electrical and plumbing are in.
 

Construction expected completion at the end of 2024.

February 2024

July 2023

Plumbing is underway throughout the building

Working on interior framing layouts and electrical riser

Exterior masonry is near completion

Trash chute is being installed

Elevator equipment is coming later this month

Curtain wall is in production

Apr 2023

Jackson Project Top Off

Dec 2022

Foundation completed on November 16th

Poured concrete on first floor on December 15th

Super structure phases going vertical

Utilities (water and sewage) brought in

Aug-Sep 2022

Early stages of foundation expected to be completed by end of Q4/2022

Mar 2022

bottom of page