38th Ave
May 2024
Delivery of materials are on time. Installation is commenced.
Framing will be completed, sheetrock will be installed.
Plumbing and electrical will continue being installed.
Once the connections are ready, installation of appliances will be commenced.
Construction expected to complete at the end of 2024.
Nov 2023
Topped out
Expected completion Quarter 4 of 2024
Sep 2023
Construction progressing on schedule with current 5th Floor completion this month
Continue to project completion by the 4th Quarter of 2024
Apr 2023
Construction site is active with SOE (Support with Excavation) activity in full operation
Expect to complete SOE by mid-May
Excavation is scheduled to commence immediately following before the end of May
Pouring concrete footings/forms will follow with foundation expected to commence in June
Aug 2022
Pre-construction & development efforts continue with expected construction commenced by end of Q4/2022
June 2022
Break ground ceremony held on June 14th.
Thomson
Apr 2023
CO obtained in Fall 2022
Residents have moved in
Sep 2022
Construction is completed.
CO obtained for lower floors of rental units. Applied for CO for upper floors.
Earliest move in date is set for September 15th.
Aug 2022
Substantial completion expected by end of this month
TCO to be applied next month
Launched to the market on August 16th
June 2022