Group 13

38th Ave/Thomson

Project Progress

38th Ave

May 2024

Delivery of materials are on time. Installation is commenced.


Framing will be completed, sheetrock will be installed.


Plumbing and electrical will continue being installed.


Once the connections are ready, installation of appliances will be commenced.


Construction expected to complete at the end of 2024.

Nov 2023

Topped out

 

Expected completion Quarter 4 of 2024 

Sep 2023

Construction progressing on schedule with current 5th Floor completion this month

 

Continue to project completion by the 4th Quarter of 2024

Jul 2023

Commencing superstructure

 

Top off expected in Q3 of 2023

 

Expected completion at the end of 2024 

Apr 2023

Construction site is active with SOE (Support with Excavation) activity in full operation

 

Expect to complete  SOE by mid-May

 

Excavation is scheduled to commence immediately following before the end of May

 

Pouring concrete footings/forms will follow with foundation expected to commence in June 

Aug 2022

Pre-construction & development efforts continue with expected construction commenced by end of Q4/2022

June 2022

Break ground ceremony held on June 14th.

Thomson

Apr 2023

CO obtained in Fall 2022

Residents have moved in

Sep 2022

Construction is completed.

CO obtained for lower floors of rental units. Applied for CO for upper floors.

Earliest move in date is set for September 15th.

Aug 2022

Substantial completion expected by end of this month

 

TCO to be applied next month

 

Launched to the market on August 16th

June 2022