top of page
露台-2.jpg

Group 15 Dutch Kills 

Project Progress

Project A

Aug 2024

Stop work order has been lifted, construction work is now resumed.

Foundation work on-going, expected completion early November.

Dec 2023

Project had its break ground ceremony on Dec 19th, 2023.

Oct 2023

Project has topped out.

Project B

Aug 2024

Condos are 60% sold.

The framing of all condominium units has been completed.

The installation of sheetrock has begun and is expected to completed one floor a week.

Window framing has been fully completed and window installation is expected to begin at the end of August.

Construction of the exterior walls and glazing expected to be completed by mid-October;

Both residential elevators are in place;

Sprinklers have been installed from the 2nd floor to 9th floor;

Bathtubs for all condominium units have arrived and have been installed up to the 6th floor.

Dec 2023

Project has topped out.

Oct 2023

Project had its break ground ceremony on Dec 19th, 2023.

bottom of page